General schedule
PI 20 |
PI 21 |
PI 22 |
PI 23 |
Nov | CMS Login Dashboard |
Feb | Assignments ↑ | May | Launch Strategy Settings ↑ Notifications |
Aug | Launch |
Dec | Login Class Materials |
Mar | Markbook ↑ | Jun | Communications BE Integration ↑ |
||
Jan | Class Materials iRead |
Apr | Reports BE Integration ↑ |
Jul | Testing |
Detailed schedule
Week | Days | Activity |
Week 1-2 Preparation and Configuration |
Preparation of the testing environment. | |
Definition of necessary variables for the application. | ||
Week 3
Unit and Integration Testing |
Execute automated unit tests, document, and correct any errors found. | |
Execute integration tests to validate interaction between modules, document, and correct any errors found. | ||
Analysis of unit and integration test results, adjustments, and improvements based on the findings. | ||
Week 4 System testing |
Execute system tests to validate the complete functionality of the platform, document, and correct any errors found. | |
Analysis of system test results, adjustments, and improvements based on the findings. | ||
Week 5
Performance testing |
Configuration of performance testing tools, definition of test scenarios. | |
Perform load tests, monitor system performance. | ||
Analysis of performance test results and areas for improvement. | ||
Week 6 Safety testing |
Configuration of security testing tools, definition of test scenarios. | |
Execute penetration and vulnerability tests, document and correct vulnerabilities found. | ||
Analysis of security test results, implementation of additional security measures if necessary. | ||
Week 7
User acceptance testing. |
Setting up the environment for the user, selecting test cases based on user requirements. | |
Key users execute test cases, document, and correct errors found. | ||
Analysis of results, final approval by users. | ||
Week 8
Final review and preparation for deployment into production. |
Final review of all test results, update of technical and user documentation. | |
Implementation of final adjustments based on test results, optimization of performance and security. | ||
Planning and communication of the production deployment plan, final validation of the production environment. |
Additional Considerations
- Communication:
- Maintain constant communication with the development and testing teams to quickly resolve issues.
- Hold meetings to review progress and obstacles.
- Flexibility:
- The schedule is flexible to accommodate unforeseen events and new discoveries during testing.
- Documentation:
- Document all findings, errors, and adjustments made during the testing process.